Work continues on the new cancer facility in Kearney, Nebraska, that is targeted to open in late 2024.
As seen in the photo above, the building is taking shape, and upcoming work being done at the site includes the following:
- Installing the curtain wall glass on both the north and south sides of the building.
- Paving the south parking lot.
- Setting and connecting the air handling units by the end of the month.
Upcoming work in August and September includes:
- Installation of the CT and linear accelerator (LINAC) equipment in late August.
- Start the landscaping and buildout of the healing garden in September.
Wow!! Good job UNMC!! Patient’s can get the great care almost all over Nebraska in big cities!!
Looking good